here's our timeline: ~Manila Visa Office~

March 2, 2010: Application sent to NS
May 11: 1st AOR received
May 26: 2nd AOR received
June 02: ECAS (received by VO)
July 28: ECAS (in process); Medical Request Sent by VO
August 3: Received Medical Request
August 11: Med done/RPRF sent
August 16: Additional x-ray
August 18: Meds/xray clear
August 31: DMP meds result sent to CEM
September 10: PP request
September 13: PP sent
September 28, 2010: PP with visa stamp received!! Smiley

thanks guys... and thank you Lord!!!
 
tokeneneng said:
Thank God we got our visas today!!!

here's our timeline: ~Manila Visa Office~

March 2, 2010: Application sent to NS
May 11: 1st AOR received
May 26: 2nd AOR received
June 02: ECAS (received by VO)
July 28: ECAS (in process); Medical Request Sent by VO
August 3: Received Medical Request
August 11: Med done/RPRF sent
August 16: Additional x-ray
August 18: Meds/xray clear
August 31: DMP meds result sent to CEM
September 10: PP request
September 13: PP sent
September 28, 2010: PP with visa stamp received!! Smiley

thanks guys... and thank you Lord!!!


wow congrats ang bilis. mine was sent this september din. did your ecas changed to DM?
 
tokeneneng said:
Thank God we got our visas today!!!

here's our timeline: ~Manila Visa Office~

March 2, 2010: Application sent to NS
May 11: 1st AOR received
May 26: 2nd AOR received
June 02: ECAS (received by VO)
July 28: ECAS (in process); Medical Request Sent by VO
August 3: Received Medical Request
August 11: Med done/RPRF sent
August 16: Additional x-ray
August 18: Meds/xray clear
August 31: DMP meds result sent to CEM
September 10: PP request
September 13: PP sent
September 28, 2010: PP with visa stamp received!! Smiley

thanks guys... and thank you Lord!!!

ang bilis tlga!congrats!
 
nope, ECAS hasn't changed yet.. yep, it was so fast.. God is so good!! :)

thanks m2canada and leigh_anne ! hope you'll get your visas soon!! ;)
 
tokeneneng said:
nope, ECAS hasn't changed yet.. yep, it was so fast.. God is so good!! :)

thanks m2canada and leigh_anne ! hope you'll get your visas soon!! ;)

tokeneneng, congrats!!! :) :) naku daming good news!! :_
 
tokeneneng said:
thanks imbubbles , thanks for all your informative posts!

no problem tokeneneng.. it's my way din of saying thanks :)

anyway, sent u PM! :)
 
Dear tokeneneng,

Phew!! That was fast!!!!!!!

CONGRATULATIONS!! Have a great life in Canada!!

Cheers!!
 
thanks guys, thanks for all your help!!!

to the seniors.. qorax... thanks so much!!!
 
Congrats tokeneneng! ;) ;) ;)
 
tokeneneng said:
Thank God we got our visas today!!!

here's our timeline: ~Manila Visa Office~

March 2, 2010: Application sent to NS
May 11: 1st AOR received
May 26: 2nd AOR received
June 02: ECAS (received by VO)
July 28: ECAS (in process); Medical Request Sent by VO
August 3: Received Medical Request
August 11: Med done/RPRF sent
August 16: Additional x-ray
August 18: Meds/xray clear
August 31: DMP meds result sent to CEM
September 10: PP request
September 13: PP sent
September 28, 2010: PP with visa stamp received!! Smiley

thanks guys... and thank you Lord!!!
Congrats