sachinsoman1988 said:
Dude! I an am AOR in March 2016, and here is my job title and related details:
Instrumentation and Control Engineer
Main duties included in the letter:
- Presentation of control engineering activities, time schedule, and progress report
- Preparing EPC tender documents
- Preparing control system specification for DCS
- Preparing wiring diagram and control panel layout
- Designing and preparing control system grounding plan and grounding details of equipment
- Ordering and checking control systems equipment
- Preparing IO list for control system
- Preparing logic diagram
- Preparing control block diagram
- Designing loop diagram
- Preparing Hook-up drawings
- Designing control network layout
- Programming SIEMENS SIMATIC PCS7 PLCs and ABB 800XA DCS
- Designing cable route and cable schedule
- Preparing test procedures and operation manual
- Performing Factory Acceptance Test (FAT)
- Performing Site Acceptance Test (SAT)
- Providing technical support during commissioning at site
What do you think about these duties?
Do you think they are consistent with NOC 2133 or not?
Thank you in advance.